Construction conservation

Construction conservation

During the construction process, difficulties arise and the need to suspend construction until favorable conditions appear. At the same time, the process of conservation of construction in progress requires the observance of certain procedures and causes difficulties in reflecting the costs associated with the suspension of construction.

WHAT IS CANNING?
Conservation of construction - the suspension of construction, which implies the resumption of construction work by the investor in the future. After the elimination of the reasons that led to the conservation, work at the facility continues, therefore the construction contract is not terminated, but suspended for an indefinite (or definite) period.

Stages of object conservation:
• Inventory of the facility
• Preparation of technical documentation for the conservation of the facility
• execution of an act on the suspension of construction (form No. KS-17)
• Notification of government bodies

The degree of completion of the construction can be determined as follows:

The initial stage of construction (from 0% to 15% of the volume of work) corresponds to the following level of organization of preparatory and construction works:

  • survey and design work completed;
  • identified suppliers of equipment and materials;
  • works on temporary buildings and structures within the framework of the project were completed.

The average stage of construction (over 15% to 50% of the volume of work) can correspond to the following level of organization of preparatory and construction work:

  • survey and design work completed;
  • deliveries of equipment and materials have begun and are ongoing;
  • The construction of walls and the roof structure have begun and are almost completed;
  • completed works on temporary buildings and structures under the project;
  • installation of technological equipment and internal systems has begun.

The high stage of construction (over 50% to 75% of the volume of work) corresponds to the following level of organization of construction and installation works at the facility:

  • survey work completed;
  • deliveries of equipment and materials have begun and are ongoing;
  • the construction of walls and the roof structure were completed;
  • completed works on temporary buildings and structures under the project;
  • installation of technological equipment and internal systems was performed within (50-75)%;
  • Finishing work started.

The final stage of construction (over 75% to 99% of the volume of work) corresponds to the following level of organization of construction and installation works at the facility:

  • survey and design work completed;
  • supplies of equipment and materials have been completed;
  • the construction of walls and the roof structure were completed;
  • completed works on temporary buildings and structures under the project;
  • installation of technological equipment and internal systems is being completed;
  • Finishing work at the facility was performed within (50-99)%;
  • commissioning work has begun at the facility.

LLC GARANT EXPERT, Judicial and Non-State Construction Expertise, has been operating since 2014 and during this time we managed to establish ourselves as a reliable partner for the most demanding customers. We will promptly prepare all the documentation on the suspension of construction, conservation of the object, in compliance with the requirements of the laws of construction. This will allow you to avoid difficulties when resuming work and save not only financial resources, but also precious time.
Call us today and we will do our best to best solve your problem.

Order a service: Engineering

  • This field is used for verification purposes and should be left unchanged.